Table of Contents Table of Contents
Previous Page  37 / 114 Next Page
Information
Show Menu
Previous Page 37 / 114 Next Page
Page Background

The US-Israel Legal Review 2019 37

By doing so, the State (through the public agency)

intends to perform the respective large-scale

infrastructure project in a relatively efficient

manner and deliver a higher quality infrastructure

facility to the public, with fewer risks (and

accordingly, costs).

In this paper I will briefly introduce some of

the most common major risks in the PPP/PFI/

BOT projects field, and provide examples of the

measures which may be taken to mitigate them,

which shall be assessed and addressed in the

respective BOT/concession agreements with the

governmental entity.

General risks (to be assumed fully/partially

by the State) which are to be incorporated and

addressed properly in the respective contracts:

• Access to the Site

– The State remains the owner

of the site during the concession period and

therefore must take all the actions required for

granting the Concessionaire an uninterrupted

and continuous access to the Site. The respective

agreement with the State shall incorporate an

appropriate mechanism addressing the event of

delays in issuance of a notice to proceed.

• Unforeseeable Soil Conditions/Findings &

Antiquities

– Since the State is the sole owner of

the site, in the event of discovering archeological

findings and/or antiquities that might cause a

suspension of the works in the project, the State

should bear the residual risk and provide certain

remedies, e.g., indemnification for direct costs,

schedule extension, etc.

• ChangeinLaw

–Oneofthemainconcernsshared

by both the Concessionaire, its contractors

and by the project’s Lenders is the risk that the

applicable laws and regulations may change

following the bid submission and adversely

affect the performance of the works within the

project. The State provides various protections

and remedies in cases where the change was

not foreseeable at the time of entering into the

contract, and to the extent that the change is

associated with additional costs and/or losses

to the Concessionaire. The adverse impact of

such change in law on the respective project

shall be evaluated on a case by case basis.

• Change Orders

– In the event of an increase

and/or amendment to the scope of work defined

in the Concession Agreement, an additional

payment due to the Concessionaire is required.

For such purpose, the Concession Agreement

shall provide for a clear mechanism for the

additional payment and the limitations thereto.

• Unjustified Suspension/Interruption

(for

reasons not attributable to the Concessionaire)

– Since the State has the ability to suspend the

works in the project, in case of an unjustified

suspension/interruption, the State should bear

the residual risk, and provide certain remedies,

NADIA DAVIDZON

PARTNER

The State provides various

protections and remedies in cases

where the change in lawwas not

forseeable at the time of entering

into the contract.