Table of Contents Table of Contents
Previous Page  38 / 114 Next Page
Information
Show Menu
Previous Page 38 / 114 Next Page
Page Background

38 The US-Israel Legal Review 2019

ISRAEL: INFRASTRUCTURE, ENERGY & PROJECT FINANCE

e.g., indemnification for direct costs, schedule

extension in the respective agreement, etc.

• Force Majeure

– Contractual clauses designated

to minimize the liability and risk to the

Concessionaire in such situations as natural

catastrophes or unavoidable circumstances,

which interfere with the planned Works that

make it difficult for the Concessionaire to fulfill

its obligations, as further detailed below.

• An exception to the risk allocation principle,

whereby the party with the most control and

knowledgewill assume all/some responsibility, is

a Force Majeure Event. These types of events are

considered exceptional, beyond the reasonable

control of either party to the Concession

Agreement.

• The assumption is that neither party could have

foreseen and prevented an event of Force Majeure

and that such event shall directly affect the

performance of the works. To define an event as

a Force Majeure event, it needs to cause material

physical damage or destruction to equipment,

or materially delays the scheduled performance

of the works and/or the State’s obligations, or

materially interrupts the Services and/or the

State’s obligations.

• Although the definition of Force Majeure may

seem broad, there are some exclusions which are

common in the Israeli PPP/PFI/BOTprojects field,

such as strikes, labor disputes, boycott lock-outs

or their similar occurrences (which are not part of

a National Strike); inclement weather conditions

(except for natural disasters); physical conditions

or obstacles above/underneath the ground/sea

level (excluding large-scale oil contamination of

seawater). War and terror events shall also be

included explicitly in such definition, in line with

the customary practice and notwithstanding the

Israeli Supreme Court’s determination that such

events are foreseeable.

• Price Adjustment

– Bilateral clause to the

State and the Concessionaire providing that

all amounts and payments payable to either

party shall be linked and adjusted to the

applicable Indices basket (to be selected by the

Concessionaire at the tender stage).

RISK ALLOCATION REGARDING PERMITS

AND AUTHORIZATIONS

The responsibility for obtaining the permits and

authorizations of the competent authorities

required for the performance of the project is

allocated between the State and the Concessionaire

and its proxies. Obtaining building permits, for

instance, is usually imposed on the Concessionaire.

Regarding other authorizations from competent

regulatory authorities (e.g., the Ministry of

Environmental Protection; Water Authority) the

allocation is commonly shared by the State and the

Concessionaire.

RISK MITIGATION

Regarding the Concessionaire, a detailed

risk analysis at the tender stage (technical,

financial and legal) has to be made. Moreover,

the Concessionaire (and sometimes its proxies)

should issue clarification requests at the

tender stage for incorporation of the required

amendments, including, for instance, with respect

to limitations of liability and liquidated damages

and providing remedies for certain significant

risks. Additionally, the Concessionaire should

enter into EPC and O&M Turn-Key Contracts, with

lump-sum payment, on a back-to-back basis (which

in recent projects is mandatory according to the

tender provisions); obtain proper securities from

the EPC & O&M Contractors (Performance and

Warranty Guarantees – autonomous, irrevocable,

unconditional bank guarantees); obtain proper

insurance; and ensure that the project is a limited

or non-recourse project (it is important to note that

the BOT projects are financed mostly by external

finance entities, i.e. banks and institutional

investors which enter into limited or non-recourse

Regarding the Concessionaire,

a detailed risk analysis at the

tender stage (technical, financial

and legal) has to be made.